| What's New || Related Link || Site Map || F.A.Q. || Contact Us |
   
 
Gridco ARR_TRF 2009-10_OERC
  TARIFF 1
TARIFF 2
TARIFF 3
TARIFF 4
TARIFF 5
TARIFF 6
TARIFF 7
TARIFF 8
TARIFF 9
TARIFF 10
TARIFF 11
TARIFF 12
TARIFF 13
TARIFF 14
TARIFF 15
TARIFF 16
TARIFF 17
TARIFF 18
TARIFF 19
TARIFF 20
TARIFF 21
TARIFF 22
TARIFF 23
TARIFF 24
TARIFF 25
TARIFF 26
TARIFF 27
Cash Flow Workings
Power Purchased

Licencee : ..GRIDCO Limited

TARIFF 1
      OERC FORM TRF-1
INFORMATION ON BLOCK CAPITAL
         
  Previous Year-2007-08      
  Current Year - 2008-09      
  Ensuing Year-2009-10      
      Rs. in Crores  
     FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
A. Capital employed at the       
  beginning of the year      
         
  (a) On completed works - 0.04   0.54
         
  (b) On works in progress - - -
         
  Sub Total : - 0.04   0.54
         
B. Capital employed during the year      
         
  (a) On completed works 0.04 0.50   1.00
  (from otherthan CWIP)      
         
  (b) On works in progress - - -
  (addition during the year in CWIP)      
  Sub Total : 0.04 0.50   1.00
         
C. Asset withdrawn, if any   -   - -
         
         
  Total (A+B-C) 0.04 0.54   1.54
         
         
         
         
  Workings      
Summary of CWIP  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
  OB - - -
  Addition during the year -    
  Transfer to Fixed Assets -    
  CB - - -
         
  Summary of Gross Fixed Assets      
  OB - 0.04   0.54
  Addition during the year from CWIP - - -
  Addition during the year otherthan CWIP 0.04 0.50   1.00
  Sale/Adjustments -    
  CB 0.04 0.54   1.54


TARIFF 2

   Project  wise / Scheme wise Capital Expenditure                     
                             
  Previous Year-2007-08                          
  Current Year - 2008-09                          
  Ensuing Year-2009-10                          
                  Rs. In Crore      Rs. In Crore   
 Sl.No   Description   PRIVIOUS YEAR (2007-08)   Current Year (2008-09)   Ensuing Year 2009-109 
   Loan/ Scheme/ Contract-wise Capital Works   OB Expenditure During the year  Interest during Construction  Transfer to Fixed Assets  Closing W I P Expenditure During the year  Interest during Construction  Transfer to Fixed Assets  Closing W I P Expenditure During the year   Interest during Construction  Transfer to Fixed Assets   Closing W I P
1 2 3 4 5 6 7=3+4+5-6 8 9 10 11=7+8+9-10 12 13 14 15=11+12+13-14
                             
                             
 Note:                             
1.As per the Transfer Nitification No.6892, dated 09-06-2005 of GoO, all the Fixed Assets & CWIP has been transferred to OPTCL.      


TARIFF 3

Information on receipt and repayment of loan (Rs. in Crores)        
Abstract                                          
  Previous Year-2007-08                                          
  Current Year - 2008-09                                          
  Ensuing Year-2009-10                                          
                                             
Sl No Particulars Rate of Interest as on 01-11-2008  OB as on 01-04-07   2007-08   2008-09   2009-10 
 Principal   Int.Outstanding   Interest due for the year   Principal   Int.Outstanding   Interest due for the year   Principal   Int.Outstanding   Interest due for the year 
Principal  Interest Outstanding   Addition   Repayment  CB as on 31-3-08    Paid   CB as on 31-3-08   Addition   Repayment  CB as on 31-3-09   To be Paid   CB as on 31-3-09   Addition   Repayment  CB as on 31-3-10    To be Paid   CB as on 31-3-10 
A Govt. Loans                                          
  State Govt.(WCL) 13.00%   120.00 125.01   - - 120.00   -  140.61   15.60   -   -   120.00   -   156.21   15.60 - 90.00   30.00 15.60   156.21   15.60
  St.Govt (OPGC Adj.) 10.50%   42.54 30.29   - -   42.54   - 34.76   4.47   -   -   42.54   -   39.23   4.47 - 26.30   16.24 4.47 39.23 4.47
  NTPC (Govt.Bonds) 8.50%   1,047.73   -   -   110.29 937.44 86.59   -   86.59   -   110.29   827.16 77.44 -   77.44 -   110.29   716.87 67.96   -   67.96
  Sub Total     1,210.27 155.31   -   110.29   1,099.98 86.59  175.37 106.65   -   110.29   989.70 77.44   195.44   97.51 -   226.59   763.11 88.03   195.44   88.03
B Institutional Loans                                          
  REC- Term Loan 10.61%   93.07   -   -   68.56   24.51 6.60   -   6.60   - 24.51 - 0.54 -   0.54 -   - -   -   - -
  REC- WCL 8.00%   125.00   -     125.00 - 4.60   -   4.60   -   - -   - - - -   - -   -   - -
  OPTCL-STL 10.00%   26.00 0.01 44.00   70.00 - 2.55   -   2.54   -   - -   - - - -   - -   -   - -
  Sub Total     244.07 0.01 44.00   263.56   24.51 13.75   -   13.74   - 24.51 - 0.54 -   0.54 -   - -   -   - -
C Secured Loan                                          
  Union Bank of India- I 8.25%   45.74   -   -   16.70   29.04 3.11   -   3.11   - 16.67   12.37 1.77 -   1.77 - 12.37 - 0.42   - 0.42
  Union Bank of India- III 11.50%   91.66   -   -   14.40   77.26 9.05   -   9.05   - 14.29   62.97 7.93 -   7.93 - 14.29   48.69 6.49   - 6.49
  Union Bank of India- IV 12.75%   100.00 0.03   -   0.09   99.91 12.04   -   12.01   - 17.88   82.03 11.41 -   11.41 - 16.67   65.36 9.49   - 9.49
  Allahabad Bank - I 8.25%   14.27   -   -   3.57   10.69 1.07   -   1.07   - 3.57 7.12 0.77 -   0.77 - 3.57   3.55 0.48   - 0.48
  Allahabad Bank - II 8.25%   60.71   -   -   10.72   49.99 4.60   -   4.60   - 10.72   39.27 3.72 -   3.72 - 10.72   28.55 2.84   - 2.84
  Allahabad Bank - III 8.25%   40.48   -   -   7.14   33.33 3.07   -   3.07   - 7.14   26.19 2.48 -   2.48 - 7.14   19.05 1.89   - 1.89
  Dena Bank - I 8.25%   71.61   -   -   20.04   51.57 5.07   -   5.07   - 20.04   31.53 3.42 -   3.42 - 20.04   11.49 1.77   - 1.77
  Dena Bank  - II 8.25%   77.12   -   -   11.52   65.60 5.92   -   5.92   - 11.52   54.08 4.97 -   4.97 - 11.52   42.56 4.02   - 4.02
  Andhra Bank 10.50%   42.85   -   -   7.14   35.71 4.05   -   4.05   - 7.14   28.57 3.38 -   3.38 - 7.14   21.43 2.66   - 2.66
  Syndicate Bank 8.25%   50.00   -   -   10.00   40.00 3.75   -   3.75   - 10.00   30.00 2.92 -   2.92 - 10.00   20.00 2.10   - 2.10
  Karnataka Bank 10.75%   18.18   -   -   4.55   13.63 1.55   -   1.55   - 4.55 9.08 1.18 -   1.18 - 4.55   4.54 0.66   - 0.66
  Sub Total     612.60 0.03   -   105.88 506.72 53.27   -   53.24   -   123.51   383.21 43.95 -   43.95 -   118.00   265.21 32.81   -   32.81
D GRIDCO Bonds                                           
  OHPC-(Rs.50 Cr.) 8.50%   35.00   -   -   15.00   20.00 2.97   -   2.97   - 20.00 - 1.70 -   1.70 -   - -   -   - -
  Pension Trust Bond 9.00%   271.91 108.47   -   76.13 195.78   130.23   -   21.75   - 95.69   100.09 10.25 -   10.25 - 32.63   67.46 6.81   - 6.81
  NTPC (Rs.342.85 Cr.) 10.00%   105.10   -   -   47.85   57.25 10.99   -   10.99   - 40.39   16.87 4.72 -   4.72 - 16.87 - 0.85   - 0.85
  Sub Total     412.01 108.47   -   138.98 273.03   144.19   -   35.71   -   156.07   116.96 16.67 -   16.67 - 49.50   67.46 7.66   - 7.66
                                             
E Finance & Other Charges                                          
  Rebate & Finance Charges                   51.14       29.14     29.14           -
F Grand Total     2,478.95 263.82 44.00   618.71   1,904.25   297.80  175.37 260.49   -   414.38  1,489.87  167.75   195.44   187.82 -   394.09  1,095.78   128.49   195.44   128.49
                                             
G Less:Interest Capitalisation                 -           -           -
                                             
H Interest Chargeble                   260.49             187.82             128.49
                                             
  Average rate of interest (before Capitalisation)               12.20%           11.07%           9.94%
                                             
Note:                                          
  1. The Closing balance of Outstanding Interest is interest accrued and due but not paid.       209.35                        

TARIFF 4

CALCULATION OF COST OF POWER OF GRIDCO OERC FORM TRF-4
           
  Previous Year-2007-08        
  Current Year - 2008-09        
  Ensuing Year-2009-10        
           
SL NO Description UNIT  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
           
1 Total Power Procurement Cost RS .CR.      2,517.38      2,451.80    2,863.15
           
2 Other Cost RS .CR.        884.28         620.17       536.35
           
3 Units for Distco Drawal including Tran.Loss MU    18,113.19    18,559.16  19,608.63
           
4 Units for CPP Drawal including Trans.Loss MU          92.03         115.96        10.47
           
5 Sale of Surplus Power including UI MU      2,729.17         269.34             -  
           
6 Units Received into the system  MU    20,934.39    18,944.46  19,619.11
           
7 Total EHT Loss for Intra State Drawal in %              4.98            2.77          4.50
           
8 Less EHT Loss in the system for Intra State Sale MU            4.58            3.21          0.47
           
9 Less EHT Loss in the system for Distco Drawal MU        902.04         513.35       882.49
           
10 Energy Transmitted through the system MU    20,027.77    18,427.90  18,736.15
           
11 Energy Actually Sold in the system (Distco's+CPP) MU    17,298.60    18,158.56  18,736.15
           
  COST AT EHT        
           
1 Cost of units lost in the system RS .CR.        113.38          68.30       134.86
           
2 Cost of Trans. and cost of lost units RS .CR.          46.11          17.53        25.26
           
3 Increment cost  P/KWH          42.24          32.74        27.34
           
4 Power Procurement Cost P/KWH        120.25         129.42       145.94
           
5 Element of Profit (Return on Equity) P/KWH               -                 -            3.09
           
6 Total Cost with Profit P/KWH        162.49         162.16       176.36

TARIFF 5

 REVENUE REQUIREMENT    OERC FORM TRF-5
Expenditure      
Para XVII Clause-2 (b) of Schedule VI of Elec. (Supply) Act 1948    
           
    Previous Year-2007-08      
    Current Year - 2008-09      
    Ensuing Year-2009-10      
        Rs. In Crore
       FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
SL NO Description      
           
I.    Cost of Purchase of Energy   2,517.38    2,451.80    2,863.15
Note: From FY-03-04, as proposed by R&T Branch          
II.   Transmission Cost (O/M)      
  (a) Employees cost           1.74          11.48           6.05
  (b) R & M Cost               -                  -             0.50
  (c) Admn. & General Expenses           0.94            1.04           1.09
  (d) Amortisation of approved investment for restoring damages due to cyclone.               -                  -                  -  
           
III.   Rent, rates and taxes other than all taxed on Imcome & Profits           0.83            1.03           1.03
           
IV.   Interest on loans, advanced by Gridco      
  (a) Interest on loan borrowed from organisation less Interest capitalisation & Interest in distco Loan      260.49       187.82       128.49
  (b) Interest on debenture issued by licensee      
           
V.   Interest on security deposit               -                  -                  -  
           
VI.   Legal charges ( shown separately from A&G Expenses)           1.29            2.64           3.00
VII.   Provision for Bad debt               -                  -                  -  
VIII.   Auditor's fees ( shown separately from A&G Expense)           0.02            0.02           0.02
IX.   Management including managing agents remuneration               -                  -                  -  
X.   Depreciation           0.00                -                  -  
XI.   Other expenses    (ERLDC Fees)               -              1.32           1.32
XII.   Contribution to P.F., Staff pension,Gratuity (Included in Employee Cost)           0.26            0.45           0.76
  (a) Expenses on training & other training scheme               -                  -                  -  
    Bonus      
    Provision of Principal Repayment in lieu of Depreciation      618.71       414.38       394.09
A   (Total expenses I to XIII)   3,401.66    3,071.97    3,399.50
           
Special appropriation to cover      
Para XVII Clause 2(c)      
       FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
SL NO Description      
I.   Uncoverd expenses  to the extent for revision of Bulk Supply Price for FY  2008-09 to the extent on Revised of BSP Pettion Application               -                  -         472.23
           
II.   All taxes on income & profits      
III.   Installments of written down account      
    in respect of intangible assets and      
    new capital issue expenses      
IV.   Contribution to contingency reserve               -                  -                  -  
V.   Contribution towards arrear depreciation      
  (a) Contribution to development reserve      
  (b) Debt redemption and obligation      
VI.   Other special appropriation permitted      
    by Appropriate Authority      
B   Total of (I to VI)               -                  -         472.23
C   Total (A+B)   3,401.66    3,071.97    3,871.73
D   Return on Equity @ 14%               -                  -           60.62
E   Rebate to Consumers               -                  -                  -  
F   Miscellaneous Receipts   1,253.45       272.48           3.30
    Total (C+D+E-F)   2,148.20    2,799.49    3,929.05
Note: As per the GoO Notification no.1068, 29-1-2003, the reasonable return is taken as Nil till the Sector become Viable.

TARIFF 6

    CALCULATION OF CLEAR PROFIT FOR THE ENSUING FINANCIAL YEARS
  AS PER THE SCHEDULE VI OF ELECTRICITY SUPPLY ACT, 1948  
PARA  - XVII (2)      
      Rs. in Crores
    Income derived from :  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
           
(A) i) Gross receipt from Sale of energy   2,094.80   2,206.96    2,288.10
     less: Rebate allowed to DISTCOs            -               -               -  
    Net receipt from Sale of energy to DISTCOS  2,094.80   2,206.96    2,288.10
    Gross receipt from direct  Sale of energy to other than DISTCOS less discounts applicable thereto.      
    Sale of Surplus Power including UI  1,124.06      196.11             -  
    Intra State Sale       27.78        37.59          3.30
  ii) Rental of meters and other apparatus hired to customer            -               -               -  
  iii) ****      
  iv) Rents less out goings otherwise provided for      
  v) Transfer fees      
  vi) Investment fixed & call deposits & bank balance      
  vii) Other general receipts accountable for income tax and arising from and ancillary or incidental to business of electricity supply.      
    Inter State Wheeling of Power            -               -               -  
    Intra State Wheeling of Power            -               -               -  
    Unscheduled Interchange            -               -               -  
    Delay Payment Surcharge            -               -               -  
    Other Misc.Receipt     101.62        38.78             -  
    Total of (A) (i to vii)  3,348.25   2,479.44    2,291.40
           
(B)   Expenditure properly incurred on :      
  i)  Cost of Purchase of Energy  2,517.38   2,451.80    2,863.15
    Power Purchase       2,372.00       2,359.47        2,863.15
    Wheeling to Discoms         145.38            92.32                  -  
  ii) Transmission Cost (O/M)      
    a)  Employees cost        1.74        11.48          6.05
    b)  R & M             -               -            0.50
    c)  A&G expenses        0.94          1.04          1.09
    d) Amortisation of approved investment for restoring damages due to cyclone.            -               -               -  
  iii) Rents, rates & taxes, other than all taxed on income and profit        0.83          1.03          1.03
  iv) Interest on loan advanced by Board       
  iv.a) Interest on loan borrowed from Organisation less interest Capitalisation & Interest on Distco Loan     260.49      187.82      128.49
  iv.b) Interest on debenture issued by licensee            -               -               -  
  v) Interest on security deposit            -               -               -  
  vi) Legal charges        1.29          2.64          3.00
  vii) Bad debts            -               -               -  
  viii) Auditors fees        0.02          0.02          0.02
  ix) Management including managing agents remuneration            -               -               -  
  x) Depreciation        0.00             -               -  
  xi) Other expenses    (ERLDC Fees & License Fees)            -            1.32          1.32
  xii) Contribution to P.F., staff pension and gratuity        0.26          0.45          0.76
  xii.a) Expenses on apprentice & other training scheme            -               -               -  
  xiii) Bonus            -               -               -  
    Provision of Principal Repayment in lieu of Depreciation     618.71      414.38      394.09
    Provision towards Trading of Power            -       (615.03)             -  
    Prior period Expencess/(income)       (0.77)             -               -  
  Total expenditure i.e. total of (B) (i to xiii)    3,400.89   2,456.94    3,399.50
           
(C)   Special appropriation to cover :      
  i) Uncoverd expenses  to the extent for revision of Bulk Supply Price for FY  2008-09 to the extent on Revised of BSP Pettion Application            -               -        472.23
  ii) All tax on income and profits        0.03             -               -  
  iii) Instalments of written down amounts in respect of intangible asset and new capital issue expenses      
  iv) Contribution to contingency reserve            -               -               -  
  v) Contribution towards arrear depreciation      
  v.a) Contribution to Development Reserve, referred to in para      
  v.b) Debt redemption obligation      
  vi) Other special appropriation permitted by the State Govt.      
           
    Total of (C) (i to vi)        0.03             -        472.23
           
    CLEAR PROFIT (A-B-C)      (52.66)        22.50   (1,580.33)
           
    Return on Equity @14%            -               -          60.62
           
    Excess or deficit of clear profit over reasonable return      (52.66)        22.50   (1,640.95)

TARIFF 7

CALCULATION OF CAPITAL BASE AND REASONABLE RETURN FOR ENSUING FINANCIAL YEAR (FY 2009-10)
     
[In accordance with para XVII of Schedule VI of Electricity (Supply) Act, 1948]      
       (Rs. in Crores.) 
     FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
         
A.        
(a) Original cost of fixed asset   Less  contribution for deposit works                -                  -                  -  
         
(b) Cost of intangible asset                -                  -                  -  
         
(c) The original cost of Work in progress                -                  -                  -  
         
(d) The amount of investment compulsorily made under para-IV                -                  -                  -  
         
(e) An amount on account of working capital equal to the sum of       
  (i)   Average cost of stores                 -                  -                  -  
  (1/12th of the sum of the stores materials and suppliers      
   at the end of each month of the year)      
  (ii)    Average cash and bank balance                -                  -                  -  
  (1/12th of the sum of cash and bank balance whether credit      
  or debit and call and short term deposits at the end of each      
  month of the year)      
         
Total of A:                  -                  -                  -  
         
Less        
B.        
i) The amounts written off or set aside on account of depreciation                -                  -                  -  
  of fixed assets.      
ii) The amount of any loan advanced by Board.                -                  -                  -  
ii-a) The amount of any loans borrowed from organisations or institutions approved by the State Govt.      
ii-b) The amount of any debenture issued by the licensee.      
iii) ***      
iv) The amount standing to the credit of Tariffs and Dividends control reserve at the beginning of the year of account.      
v) The amount standing to the credit of the Development reserve at the close of the year.      
vi) The amount carried forward (at the beginning of the year of accounting) in the accounts of the Licensee for distribution       
         
Total of B:                  -                  -                  -  
  Capital Base (A-B)                -                  -                  -  
         
  Reasonable return      
a) RBI rate at the beginning of that year + 5% on investment made upto 31.3.99 +                -                  -                  -  
b) 14% on investment made after 31.3.99 +                -                  -                  -  
c) 0.5% of loan outstanding as at the end of the year                -                  -                  -  
  TOTAL (a+b+c)                -                  -                  -  
       
       Rs. In Cr. 
Sl No Calculation of Reasonable Return      
         
1 Capital Base allowed by the Commission in its Tariff Order Dated 21.12.98 for the year 98-99      
2 Capital Base Calculated for the year                 -                  -                  -  
3 Additional Capital Base during the period from 31.03.99 to till end of Financial year                -                  -                  -  
4 13% Return on Capital Base as on 31.03.99                -                  -                  -  
5 16% Return on additional investment                -                  -                  -  
6 0.5% on Loan Outstanding                -                  -                  -  
7 Total Reasonable Return                -                  -                  -  
       
NB: This statement is not required for Gridco.    

TARIFF 8

Proposed Charges, other than and in addition to    OERC FORM  TRF-8
the charges of tariff leviable for the purpose       
       
(a) MONTHLY METER RENT   Existing Proposed
         
1 LT Metering      
2 11 KV Metering      
3 33 KV Metering       
4 EHT Metering       
         
(B) BASIS OF CALCULATION OF MONTHLY METER RENT      
         
NB: This statement is not required for Gridco.  

TARIFF 9

Statement of sundry debtors and provision for bad & doubtful debt  
         
  Previous Year-2007-08   OERC FORM  TRF-9
  Current Year - 2008-09      
  Ensuing Year-2009-10      
      Rs. in Crs.  
Sl. No Particulars      
     FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
1 Receivable from DISTCOS & others at the beginning of the year     1,533.84     1,355.78   1,153.04
         
2 Net Revenue billed for the year    3,246.64     2,440.66   2,291.40
         
3 Collection for the year    3,424.69     2,643.40   2,419.14
  Against current dues     2,976.08     2,237.27   2,100.45
  Against arrears upto previous year        448.61        406.13      318.69
         
4 Gross receivable from DISTCO & others  as at the end of the year    1,355.78     1,153.04   1,025.30
         
5 No of days gross receivable represents to sales Revenue        152.42        172.44      163.32
         
6 Provision  for bad and doubtful debts                  -                   -                 -  
         
7 % of provision (item 6 expressed as a percentage of item 4)                 -                   -                 -  
         
         
Statement showing Calculation of Provision for Bad & Doubtful Debtors on Wheeling sale       
Sl. No Particulars  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt) 
         
1 Wheeling Charges for the inter state sale for the year                 -                   -                 -  
         
2 Wheeling Charges for the intra state sale for the year                 -                   -                 -  
         
3 Provision  for bad and doubtful debts                  -                   -                 -  
         

TARIFF 10

INFORMATION ON INVENTORY 
  Previous Year-2007-08                        
  Current Year - 2008-09   PERIOD- 1 ACTUALS FOR PREVIOUS YEAR              
  Ensuing Year-2009-10     2 ACTUALS FOR IST SIX MONTHS OF THE CURRENT YEAR          
        3 EXPECTED FOR LAST SIX MONTHS OF THE CURRENT YEAR         Rs. in Crs.
        4 EXPECTED FOR ENSUING YEAR              
                           
Sl. Particulars April May June July August Sept. Oct. Nov. Dec. Jan. Feb. March
No.                          
                           
1 Opening Stock                        
                           
2 Purchase during the month                        
                           
3 Issue for consumption                        
                           
4 Adjustment                        
  (Write-off)                        
                           
5 Closing Stock                        
  (1+2-3-4)                        
Note:                         
This statement is not required for Gridco.                    

TARIFF 11

Licencee:- GRIDCO Limited. OERC FORM  TRF-11
 INFORMATION OF CASH & BANK BALANCE   
                             
  Previous Year-2007-08                          
  Current Year - 2008-09                          
  Ensuing Year-2009-10                          
                             
 1. Provisionals FOR PREVIOUS YEAR - 2007-08                   (Rs. in Crores)   
 Sl. No.   Particulars   April   May   June   July   Aug.   Sept.   Oct.   Nov.   Dec.   Jan.   Feb.   March   Total 
         1  Opening Balance      105.47       77.27     123.05       73.12     130.01     198.90     267.65     140.19        345.47        400.35         429.05         451.93        105.47
         2  Receipt      357.60     327.64     365.82     261.19     390.58     351.93     310.71     514.77        347.78        352.02         310.64         368.39     4,259.07
         3  Payment      385.80     281.86     415.74     204.30     321.70     283.17     438.17     309.50        292.90        323.33         287.76         540.51     4,084.73
         4  Balance        77.27     123.05       73.12     130.01     198.90     267.65     140.19     345.47        400.35        429.05         451.93         279.81        279.81
                             
 2. ACTUALS FOR FIRST SIX MONTHS OF THE CURRENT YEAR - 2008-09 
 Sl. No.   Particulars   April   May   June   July   Aug.   Sept.   Oct.   Nov.   Dec.   Jan.   Feb.   March   Total 
         1  Opening Balance      279.81     204.86     120.58     135.71     147.82     155.45                    279.81
         2  Receipt      307.17     286.97     213.02     278.58     332.82     275.81                 1,694.37
         3  Payment      382.12     371.25     197.88     266.47     325.19     283.01                 1,825.92
         4  Balance      204.86     120.58     135.71     147.82     155.45     148.25                    148.25
                             
 3. EXPECTED FOR 2nd. SIX MONTHS OF THE CURRENT YEAR - 2008-09 
 Sl. No.   Particulars   April   May   June   July   Aug.   Sept.   Oct.   Nov.   Dec.   Jan.   Feb.   March   Total 
         1  Opening Balance                  148.25       75.67          27.53         (15.42)          (55.89)       (110.61)        148.25
         2  Receipt                  308.26     199.94        206.62        208.57         210.99         275.87     1,410.25
         3  Payment                  380.85     248.09        249.56        249.03         265.72         345.87     1,739.12
         4  Balance                    75.67       27.53         (15.42)         (55.89)        (110.61)       (180.61)       (180.61)
                             
 4. EXPECTED FOR ENSUING YEAR - 2009-10 
 Sl. No.   Particulars   April   May   June   July   Aug.   Sept.   Oct.   Nov.   Dec.   Jan.   Feb.   March   Total 
         1  Opening Balance    (180.61)   (258.37)   (338.73)   (416.48)   (496.84)   (577.19)   (654.95)   (735.30)       (813.06)       (893.41)        (973.76)    (1,046.34)       (180.61)
         2  Receipt      198.83     205.46     198.83     205.46     205.46     198.83     205.46     198.83        205.46        205.46         185.58         205.46     2,419.14
         3  Payment      276.59     285.81     276.59     285.81     285.81     276.59     285.81     276.59        285.81        285.81         258.15         285.81     3,365.22
         4  Balance    (258.37)   (338.73)   (416.48)   (496.84)   (577.19)   (654.95)   (735.30)   (813.06)       (893.41)       (973.76)    (1,046.34)    (1,126.69)   (1,126.69)

TARIFF 12

Previous Year-2007-08 OERC FORM  TRF-12
  Current Year - 2008-09          
  Ensuing Year-2009-10          
           
STATEMENT OF SHARE CAPITAL (PREVIOUS YEAR, CURRENT YEAR & ENSUING YEAR)
          (Rs. in Crs.)
STATEMENT OF SHARE CAPITAL FOR THE F.Y.2007-08 (Actual)      
  Description of capital Balance at the Beginning of the Year-2007-08 Receipts during the Year Redeemed during the Year Balance at the end of the Year-07-08 Remarks
  1 2 3 4 5 6
A Share capital 432.98             432.98  
a Authorised capital (Rs In crores)      1,000.00            -                 -        1,000.00  
b Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
c % preference shares of Rs. Each                -              -                 -                  -    
d Issued capital (Rs in Crores)         432.98            -                 -           432.98  
e Ordinary shares of Rs. Each      1,000.00            -                 -      
f % preference shares of Rs. Each                -              -                 -      
g Subscribed capital (Rs In Crores)         432.98            -                 -           432.98  
h Ordinary shares of Rs. Each      1,000.00            -                 -      
I % preference shares of Rs. Each                -              -                 -      
j Called-up capital (Rs In Crores)         432.98            -                 -           432.98  
k Ordinary shares of Rs. Each      1,000.00            -                 -      
l % preference shares of Rs. Each                -              -                 -      
m Less calls in arrears                -              -                 -      
n Paid up capital (Rs In Crores)         432.98            -                 -           432.98  
o Ordinary shares of Rs. Each      1,000.00            -                 -      
p % preference shares of Rs. Each                -              -                 -      
  Total paid up capital (Rs In crores)         432.98            -                 -           432.98  
             
STATEMENT OF SHARE CAPITAL FOR THE F.Y.2008-09 (Estt.)        
  Description of capital Balance at the Beginning of the Year-08-09 Receipts during the Year Redeemed during the Year Balance at the end of the Year-08-09 Remarks
  1 2 3 4 5 6
A Share capital         432.98            -                 -           432.98  
a Authorised capital (Rs In crores)      1,000.00            -                 -        1,000.00  
b Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
c % preference shares of Rs. Each                -              -                 -                  -    
d Issued capital (Rs in Crores)         432.98            -                 -           432.98  
e Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
f % preference shares of Rs. Each                -              -                 -                  -    
g Subscribed capital (Rs In Crores)         432.98            -                 -           432.98  
h Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
I % preference shares of Rs. Each                -              -                 -                  -    
j Called-up capital (Rs In Crores)         432.98            -                 -           432.98  
k Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
l % preference shares of Rs. Each                -              -                 -                  -    
m Less calls in arrears                -              -                 -                  -    
n Paid up capital (Rs In Crores)         432.98            -                 -           432.98  
o Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
p % preference shares of Rs. Each                -              -                 -                  -    
  Total paid up capital (Rs In crores)         432.98            -                 -           432.98  
             
STATEMENT OF SHARE CAPITAL FOR THE F.Y.2009-10(ESTIMATE)      
  Description of capital Balance at the Beginning of the Year-09-10 Receipts during the Year Redeemed during the Year Balance at the end of the Year-09-10 Remarks
  1 2 3 4 5 6
A Share capital         432.98            -                 -           432.98  
a Authorised capital (Rs In crores)      1,000.00            -                 -        1,000.00  
b Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
c % preference shares of Rs. Each                -              -                 -                  -    
d Issued capital (Rs in Crores)         432.98            -                 -           432.98  
e Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
f % preference shares of Rs. Each                -              -                 -                  -    
g Subscribed capital (Rs In Crores)         432.98            -                 -           432.98  
h Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
I % preference shares of Rs. Each                -              -                 -                  -    
j Called-up capital (Rs In Crores)         432.98            -                 -           432.98  
k Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
l % preference shares of Rs. Each                -              -                 -                  -    
m Less calls in arrears                -              -                 -                  -    
n Paid up capital (Rs In Crores)         432.98            -                 -           432.98  
o Ordinary shares of Rs. Each      1,000.00            -                 -        1,000.00  
p % preference shares of Rs. Each                -                      -    
  Total paid up capital (Rs In crores)         432.98            -                 -           432.98  

TARIFF 13

Previous Year-2007-08 OERC FORM  TRF-13
Current Year - 2008-09        
Ensuing Year-2009-10        
           
EMPLOYEES COST 
    Rs.in Crores    
SL.NO. Particulars  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt)  Assumptions   (% increase over Last FY)
           
1  Salaries              1.08               1.12                   1.89 Assuming 86% Increase on Basic pay of Previous Year Plus @Rs.5000 GP of 70 employes 
2  Over-time                   -                     -                          -   Nil
3 Dearness Allowance              0.44               0.57                   0.49 Assuming  DA rate for FY 2008-09 is 16% prevalent  during  month of July as per 6PC and 26% DA proposed for FY 2009-10)
4 Other Allowance              0.01               0.46                   0.50 Assuming  DA & TA for Training &  Tour etc 
5 Bonus              0.00               0.02                   0.02 Fixed
6 Sub Total (1 to 5)              1.54               2.17                   2.90  
           
  OTHER STAFF COST        
7  Reimbursement of Medical Expenses              0.05               0.08                   0.19 10% of Basic(allw and/or reimb)
8 Leave Travel Concession              0.00               0.10                   0.10 fixed
9 Reimbursement of House Rent              0.12               0.22                   0.38 20% of Basic
10 Interim Relief to Staff                   -                     -                          -    
11 Encashment of Earned Leave                   -                     -                          -    
12 Honorarium                   -                 0.25                   0.30 Contractual engagement  plus Service Charge
13  Payment under Workmen compensation Act                   -                     -                          -    
14 Ex-gratia              0.02               0.09                   0.11  @ Rs15000/- per Emp 
15 Miscellaneous              0.02               0.05                   0.06 Fixed
16 Staff Welfare Expenses                   -                 0.02                   0.09 5% of Basic Pay
17 Terminal Benefits              0.26               0.45                   0.76 40% of Basic
18 Sub Total  (7 to 17)              0.46               1.26                   1.98  
19 Arrear HRA                    -                 8.50                        -   Arrear HRA to Executive from 1998 to 2006 at revised rate (20%)
20 Provision for Sixth Pay  Arrear                    -                     -                     1.92 Assuming 2007-08 as Mid year for 6pc Arrear, arrear amounts is [ {(Basic/1.5 x 1.86*1.03*+70*.0006*12)x12% DA}-(Basic+DA)]x3.25
21 Sub Total  (19 & 20)                   -                 8.50                   1.92  
22 Total (6+18+21)              2.00            11.93                   6.80  
  Less :Capitalisation                   -                     -                          -    
  Net Total              2.00            11.93                   6.80  
           
  ADDITIONAL INFORMATION        
1 No. of Employees as on1.4.06 :        
2 No. of Employees per MKWh sold        
3 No. of consumer as at ...............        
4  No. of employees per 1000 consumers        
           
  Note:        
1 The above projection has been made without considering the future increase by the sixth pay commission.
2 Hon'ble Commission may factor a suitable increase keeping in view the forthcoming recommendation 
   of sixth pay commission        

TARIFF 14

Previous Year-2007-08
Current Year - 2008-09        
Ensuing Year-2009-10        
         
         
REPAIRS AND MAINTENANCE EXPENSES 
         
   FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt)  Assumptions (% increase over Last FY)
Description        
Civil repairs & maintenance                -                  -                    -    
Transmission line repairs & maintenance                -                  -                    -    
Building repair & maintenance                -                  -                    -    
Vehicle repair & maintenance                -                  -                0.20 Fixed
Furniture & Fixture repair & maintenance                -                  -                0.10 Fixed
Office equipment repair & maintenance                -                  -                0.20 Fixed
Hydrulic Works repair & maintenance                -                  -                    -    
Plant & machinary repair & maintenance                -                  -                    -    
TOTAL                -                  -                0.50  
Less: Capitalisation                -                  -                    -    
Net Repair & Maintenance                -                  -                0.50  
         
Note - The R&M Cost   has estimated on use specific head of expenditure.  

TARIFF 15

OERC FORM  TRF-15
  Previous Year-2007-08        
  Current Year - 2008-09        
  Ensuing Year-2009-10        
           
ADMINISTRATION & GENERAL EXPENSES    
Accot Code Description  FY-07-08 (Actual)   FY-08-09 (Estt)   FY-09-10 (Estt)  Assumptions    (% Rise over FY 07-08)
           
76.1 PROPERTY RELATED EXPENSES        
  Licence Fees           0.80         1.00         1.00 Annual escalation
  Rent           0.03         0.03         0.03 @5.5% over the
  Rates & Taxes           0.00         0.00         0.00 previous year
  Insurance           0.00         0.00         0.00 based on the 
  Contribution to accident reserve fund                -                -                -   approval of 
  Others                -                -                -   ARR'2007-08 except 
  Sub total :           0.83         1.03         1.03 legal expenses, ERLDC 
76.11 COMMUNICATION                -                -   Charges & Licence Fees
  Telephone & Trunk Call           0.03         0.04         0.04  
  Postage & Telegram           0.00         0.00         0.00  
  Telex, Teleprinter Charges, Telefax                -                -                -    
  Courier Charges           0.00         0.00         0.00  
  Other                -                -                -    
  Sub total :           0.03         0.04         0.04  
76.12 PROFESSIONAL CHARGES                -                -    
  Legal expenses            1.29         2.64         3.00 Fixed
  Consultancy charges           0.00         0.05         0.05  
  Technical fees                -                -                -    
  Audit fees           0.02         0.02         0.02  
  Other charges           0.12         0.13         0.13  
  ERLDC Fees                -           1.32         1.32 Fixed
  Sub total :           1.43         4.15         4.52  
76.13 CONVEYANCE & TRAVELLING                -                -    
  Conveyance expenses           0.00         0.00         0.00  
  Travelling expenses           0.23         0.24         0.25  
  Hire charges of vehicle           0.01         0.01         0.01  
  Others           0.10         0.10         0.11  
  Sub total :           0.33         0.35         0.37  
76.15-76.16 OTHER EXPENSES                -                -    
  Fees & Subscription           0.00         0.00         0.00  
  Books & Periodicals           0.00         0.00         0.00  
  Printing & Stationery           0.03         0.03         0.03  
  Advertisement           0.03         0.03         0.03  
  Entertainment           0.01         0.01         0.01  
  Watch & Ward           0.01         0.01         0.01  
  Miscellaneous           0.24         0.26         0.27  
  Organisational Development Expenses                -                -                -    
  Donation                -                -                -    
  Training           0.02         0.02         0.02  
  Others           0.11         0.12         0.12  
  Sub total :           0.45         0.47         0.50  
76.2 MATERIAL RELATED EXPENSES        
  Demmurage and Wharfage on materials                -                -                -    
  Clearing & forwarding charges                -                -                -    
  Transit insurance                -                -                -    
  Others                -                -                -    
  Sub total :                -                -                -    
  TOTAL           3.08         6.04         6.46  
76.9 Less : Expenses Capitalised                -                -                -    
  Expenses Charged to Revenue           3.08         6.04         6.46  

TARIFF 16

CONSOLIDATED REPORT ON SECURED/UNSECURED LOAN
                               
FOR THE F.Y.2008-09 (Prov)                         (Rs. in Crores)  
                               
Source (Institution wise/Bankwise) Purpose Amount Sanctioned Date of Sanction Date of Drawal Interest Rate (%) as on       01-11-08 Tenure of Loan Moratorium period Amount of loan redeemed upto the beginning of the year Loan redemmed during the year Total loan redeemed upto the end of the year Balance of loan at the beginning of the year Balance of loan at the end of the year Interest  Penal Intt. Exchange fluctuation Other charges like finance charges, commitment charges
                                 
Union Bank of India- I Swapping of existing loans 100.00 2002-03 2002-03 8.25 8 Years 1        Year 70.96 16.67 87.63 29.04 12.37 1.77 0.00 0.00 0.00
Union Bank of India- III Swapping of existing loans 100.00 2006-07 2006-07 11.50 7.25 Years 0.25      Year 22.74 14.29 37.03 77.26 62.97 7.93 0.00 0.00 0.00
Union Bank of India- IV Swapping of existing loans 100.00 2006-07 2006-07 12.75 8 Years 1        Year 0.09 17.88 17.97 99.91 82.03 11.41 0.00 0.00 0.00
Allahabad Bank - I Swapping of existing loans 25.00 2002-03 2002-03 8.25 8 Years 1        Year 14.31 3.57 17.88 10.69 7.12 0.77 0.00 0.00 0.00
Allahabad Bank - II Swapping of existing loans 75.00 2003-04 2003-04 8.25 9                          Years 2        Year 25.01 10.72 35.73 49.99 39.27 3.72 0.00 0.00 0.00
Allahabad Bank - III Swapping of existing loans 50.00 2003-04 2003-04 8.25 9                          Years 2        Year 16.67 7.14 23.81 33.33 26.19 2.48 0.00 0.00 0.00
Dena Bank - I Swapping of existing loans 100.00 2003-04 2003-04 8.25 7 Years 2       Year 48.43 20.04 68.47 51.57 31.53 3.42 0.00 0.00 0.00
Dena Bank  - II Swapping of existing loans 80.00 2004-05 2004-05 8.25 9                          Years 2        Year 14.40 11.52 25.92 65.60 54.08 4.97 0.00 0.00 0.00
Andhra Bank Swapping of existing loans 50.00 2004-05 2004-05 10.50 8 Years 1        Year 14.29 7.14 21.43 35.71 28.57 3.38 0.00 0.00 0.00
Syndicate Bank Swapping of existing loans 50.00 2004-05 2004-05 8.25 7 Years 2       Year 10.00 10.00 20.00 40.00 30.00 2.92 0.00 0.00 0.00
Karnataka Bank Swapping of existing loans 25.00 2004-05 2004-05 9.75 6 Years 0.5        Year 11.37 4.55 15.92 13.63 9.08 1.18 0.00 0.00 0.00
Total   755.00           248.27 123.52 371.79 506.73 383.21 43.95 0.00 0.00 0.00

TARIFF 17

CONSOLIDATED REPORT ON CAPITAL WORK-IN-PROGRESS
                       
  Previous Year-2007-08                    
  Current Year - 2008-09                    
  Ensuing Year-2009-10                    
                       
  PERIOD- 1 ACTUALS FOR PREVIOUS YEAR        
    2 ACTUALS/ESTIMATES FOR THE CURRENT YEAR    
    3 EXPECTED FOR ENSUING YEAR        
                    (Rs. in Crs.)
Scheme/ Job description Opening balance Additions         Capitalisa-tion  Adjust-ments Closing balance Last activity month Remarks
    Material Labour Contractor Others Total          
                       
                       
                       
NB: Not applicable to GRIDCO                  

TARIFF 18

CONSOLIDATED REPORT ON ADDITIONS TO FIXED ASSETS DURING THE YEAR
Previous Year-2007-08                      
Current Year - 2008-09                      
Ensuing Year-2009-10                      
                       
PERIOD- 1 ACTUALS FOR PREVIOUS YEAR            
  2 ACTUALS/ESTIMATES FOR THE CURRENT YEAR        
  3 EXPECTED FOR ENSUING YEAR            
                       
                       
Asset Description Asset code Cost         Interest Finance Charges Pre-operative expenses Exchange fluctuation Total Date of commissioning
    Material Labour Contractor Others Total            
                         
                         
                         
                       
NB: Not applicable to GRIDCO                    

TARIFF 19

OERC FORM  TRF-19
STATEMENT OF ASSETS NOT IN USE AS ON …………..
         
Previous Year-2007-08 1 ACTUALS FOR PREVIOUS YEAR  
Current Year - 2008-09 2 ACTUALS/ESTIMATES FOR THE CURRENT YEAR
Ensuing Year-2009-10 3 EXPECTED FOR ENSUING YEAR  
         
UNIT NAME & CODE : …………………………..     (Rs. in Crs.)
Sl. No. Date of Acquisition/Installation Historical Cost/Cost of Acquisition Date of withdrawal operations  Accumulated Depreciation on date of withdrawal Written down value on date of withdrawal