List of Small Hydel Plants Executed
PPAs With Gridco |
|
Sl No. |
Project Name |
Location |
Date of Execution of MoU |
Date of Execution of PPA |
Installed Capacity (MW) |
Total Project cost (Cr) |
|
1 |
M/sVENUS ENERGY PRIVATE LTD |
Onukudelli, Machkund,Dist: Koraput, Orissa |
May,2002 |
6th March 2006 |
20 |
95.86 |
|
2 |
M/s ARUN POWER PROJECTS LTD |
Hathipathar, Dist:-Rayagada, Orissa |
8th March 2004 |
18th March 2006 |
10 |
45.75 |
|
3 |
M/s KAKATIA CHEMICALS PVT. LTD |
Bargarh,Vill:-Rengali,Near Paharsrigida,
Dist:Bargarh,O
rissa |
27th October 2005 |
27th September 2006 |
9 |
36 |
|
4 |
M/s ORISSA POWER CONSORTIUM LTD. |
Vill:-Jalaput,Border of Orissa & AP,Orissa |
7th November 1994 |
28th September 2006 |
18 |
83.5 |
|
5 |
M/s SHARVANI ENERGY PRIVATE LTD |
Dumajorhi, Dist:-Koraput,Orissa |
14th September 2006 |
28th September 2006 |
15 |
72 |
|
6 |
M/s SIDHESWARI POWER GENERATION PVT. LTD |
Kharagpur, Dist:-Koraput,Orissa |
6th June 2002 |
24th October 2006 |
10 |
42 |
|
7 |
M/s JEYPORE HYDRO POWER PROJECTS PVT LTD |
At:-Sattiguda Reservoir,Jeypore Town,Dist: Koraput,Orissa |
5th July 2004 |
24th November 2006 |
6 |
27.63 |